UPROAR Press Release: 24 Jan 07 |
|
Dublin Airport's expansion plans have to be properly evaluated under the new National Development Plan. The DAA's new terminal and runway plans for Dublin Airport are included in the new National Development Plan 2007-2013. This means they will be subject to the stringent evaluation procedures that apply to all projects under the new NDP. For example, they must be subjected to a full cost benefit analysis in line with the Department of Finance guidelines of February 2005. The
Finance Guidelines should already have been applied and a cost benefit
analysis should have been done before planning permission was applied
for, as both the Terminal 2 and the new parallel runway projects will
cost vastly more than the €30 million threshold to which this
type of rigorous evaluation applies. However, the DAA admitted at
An Bord Pleanála in October 2006 that they have not done the
required cost benefit analysis. They have managed to avoid being brought
to task on this, because under the Finance Guidelines it is a matter
for the Boards of Commercial State Bodies, such as the DAA, to certify
that they have conformed to the Finance Guidelines. DAA chairman Mr
Gary McGann has told Minister Cullen that the DAA's appraisal procedures
"reflect" the Finance Guidelines, even though the DAA has
admitted it has not done the cost benefit analysis those same guidelines
require. The evaluation work done by consultants for the DAA was not
a cost benefit analysis and was clearly biased in favour of the DAA's
proposal in its lack of rigour Now
that Dublin Airport's Terminal 2 and new runway plans are included
under the new NDP it should be more difficult for the DAA to avoid
submitting to the new requirements. The NDP's tough evaluation standards
are derived from its earlier association with the EU's Structural
and Cohesion Funds. Even though very little of the new NDP will be
EU-funded, the new NDP claims it "is still largely modelled on
As spelled out on page 273 of the NDP document, all projects will be subject to project appraisal to ensure that NDP programme objectives and Value for Money are being achieved and all capital projects over €30 million will require a full cost benefit analysis in line with the Department of Finance guidelines of February 2005. A Central Monitoring Committee, chaired by the Department of Finance, will monitor implementation of the NDP. A new Central Expenditure Evaluation Unit, based in the Department of Finance, will have oversight of all reviews and can carry out spot checks on projects. Minister Cullen has hidden behind confidentiality in refusing to publish cost benefit results for projects such as the Swords Metro. However, the new NDP requires that all evaluations be published and submitted to the various oversight bodies. It will no longer be sufficient for the board chairmen of public bodies to simply claim they have conformed to the guidelines. Because
the DAA failed to carry out a cost benefit analysis as required, Portmarnock
Community Association carried out its own evaluation using cost benefit
methodology. See: www.norunway.com/t2a/appt2.htm.
We found that the expansion proposals for Dublin Airport will lead
to a loss of €4.5 billion while a second well-sited airport built
on a greenfield site to serve the Greater Dublin Area would yield
a real rate of return of 7.4%, as required by the regulator, plus
other spin-off benefits we did not quantify and which would not apply
to the Collinstown site. An We believe these findings to be robust and that a cost benefit analysis following Department of Finance and EU guidelines will confirm them. We will remain vigilant to ensure that the new evaluation procedures are properly followed in the case of the DAA's plans for Dublin Airport's unsustainable and uneconomic expansion. |