|
An Bord Pleanála
64 Marlborough Street
Dublin 1
Board
Reference: PL 06F.217429
Observations, as requested by An Bord Pleanála on 25th May 2005,
on the Environmental Impact Statement concerning the new parallel runway
at Dublin Airport in the matter of the appeal against the granting of
planning permission for that runway to the Dublin Airport Authority
on 12 April 2006 by Fingal County Council; Register Reference: F04A/1755.
| |
Matthew
Harley
60 Martello Court
Portmarnock
County Dublin
28 June 2006 |
EIS
inadequacies - summary list.
Introduction.
When the
state proposes to override the rights of citizens, decision-makers must
satisfy themselves by means of proper, complete, and prior investigation
as to the factors which should be taken into account in order to achieve
an appropriate balance between individual rights and the State's economic
interests. The burden of proof is on the State. Mere reference to the
economic well-being of the country is not sufficient to outweigh the
rights of others.
The assessment
of this runway has been totally inadequate. The national interest has
been asserted without proof. On the contrary, the proposal is demonstrably
not in the national interest.
The EIS
is not an objective or impartial document. Advantages of the proposed
runway were often exaggerated or misrepresented, while disadvantages
were understated or ignored completely. It is special pleading, rather
than analysis.
According
to the Department of Finance Guidelines for project appraisal:
 |
"Objectives
should be expressed in a way which will facilitate consideration
and analysis of alternative ways of achieving them. They should
not be so expressed as to point to only one solution." And
|
 |
"The
Sponsoring Agency [Dublin Airport Authority] is responsible for
ensuring that the appraisal is done on an objective basis and not
as a 'case-making' exercise." And:
|
 |
"It
is vital that
analysis is objective. Its conclusions should
not be prejudged. It should not be used as a device to buttress
a case already favoured for or against a proposal."
|
|
The
EIS, without even attempting to define an objective, starts as
follows:
|
 |
"Dublin Airport Authority proposes to construct a Northern
Parallel Runway at Dublin Airport."
|
 |
"The
Northern Parallel Runway is required to provide additional runway
capacity to facilitate forecast demand in passenger numbers and
associated aircraft movements at Dublin Airport." |
The EIS
shows a lack of objectivity on its first page. It is therefore not a
surprise that the conclusions arrived at support the parallel runway
option, without reservation. From the start, the EIS was designed for
that purpose. It should be rejected.
All of
the following points have been made in previous submissions to An Bord
Pleanála. They are listed here in summary form under various
headings with references to EIS chapters, where appropriate.
EIS public consultation.
The EIS
Public Consultation was held at Great Southern Hotel Dublin Airport
in October 2002. The information given then was misleading:
 |
The
proposed runway was stated to be 45 metres in width (plus shoulders)
and of comparable length to the existing 10/28 Runway. However the
submitted planning application increased the length by 11% and increased
the width to 60 metres (plus shoulders). |
Runway
building dates confusion.
The DAA
do not seem to know when this runway will be needed. All the analysis
in the EIS and Additional Information is based on confused dates. Much
of the analysis and conclusions (e.g. traffic impacts) is therefore
meaningless in the light of the operational date actually envisaged
(2013/14):
 |
In
the EIS (Chapter 5) it is stated that runway works will commence
in January 2007 and be completed by January 2010. The FCC's planning
officer confirmed in (Ref P/0436/05) that 2010 was the operational
date he considered in arriving at his conclusions.
|
 |
Table
6.8 of the EIS also implies that the new runway will be opened
by 2010.
|
 |
The
Additional Information report by RPS McHugh still states that
2010 represents the opening year for the northern parallel runway
when discussing "A revised Traffic Impact Assessment"
(p21).
|
 |
In
the DAA Annual Report 2004, it is stated that the runway will
be needed operationally in 2012.
|
 |
The
DAA's CAPEX programme supplied to the Commission for Aviation
Regulation (CAR) envisages the runway being built 2012, 2013,
and 2014.
|
 |
In
Dublin Airport's response to the CAR in 2005, (CP2/2005) it is stated
that the runway is required by 2013/2014. |
Planning
(EIS Chapter 3)
 |
Much
is made in the EIS of references in the Dublin County Development
plan of 1972 to two future east/west parallel runways at Dublin
Airport. It is claimed that, because a northern parallel runway
was envisaged in the 1972 plan, it validates their current planning
application for a northern parallel runway at Dublin Airport.
However, many developments were allowed by the Council subsequent
to 1972 that are incompatible with the northern parallel runway
envisaged in the 1972 plan and thereby overrule any historical
validity for the current runway proposal.
|
 |
The
text of the plan states in paragraph 2.18: "The Council is
aware of the Airport Authorities' intention to construct new East/West
runways and that the use of these runways will confine most of
the noise nuisance largely to lands running East/West across the
county. Approach noise will in part be absorbed over the open
sea. The Council is informed by the Airport Authority that noise
will be significant within the East/West strip and it is their
policy therefore not to make infrastructure for development available
in these lands."
|
 |
Further,
on the General County Map with the 1972 plan, the areas east and
west of the airport, and as far west as, and including Portmarnock,
are hatched in with the designation "Noise Area". "Development
Areas" are designated for Swords and Malahide, but Portmarnock
is excluded. It is quite clear that the northern parallel runway
envisaged in 1972 was predicated on the condition that Portmarnock
not be developed because of noise from its flightpath over Portmarnock.
|
 |
Subsequent
to the 1972 plan, Portmarnock was developed into a town of 10,000
people. In permitting that development in contradiction of the
1972 plan, the Council negated the northern runway component of
that plan. It is therefore disingenuous of the DAA to appeal to
that same plan in defence of its current runway proposal. If that
runway is valid on the basis of the 1972 plan, the modern town
of Portmarnock should not be there and, for consistency, would
have to be demolished.
|
 |
In
a report to the Ombudsman in late 2005, the Department of Transport
claimed that the lengthy planning history for this runway obviated
the need for a rigorous application of the Finance Guidelines on
project appraisal. Its lengthy planning history is not relevant
to the analysis of a project which is being proposed under present
and expected future conditions. On the contrary, as Lipsey put it:
"'Bygones are bygones' and they should have no influence on
deciding what is currently the most profitable thing to do." |
Engineering and Operations (EIS Chapter 4).
 |
The
NATS study cited by the EIS said a second runway would add 43
movements per hour to the capacity of the existing runway system
of 44 mph for a total of 87 aircraft mph. The method used was
flawed, as it did not account for all of the airside ground delays
incurred by aircraft.
|
 |
Experience
from Hong Kong Airport is highly relevant. A second parallel runway
at Hong Kong, with similar runway separation as proposed for Dublin,
delivered only 25 of the expected extra 40 movements per hour
on top of the 40 movements per hour from the first runway, due
to unanticipated ground movement constraints. Only 63% of the
expected gain was achieved. The current proposal for Dublin Airport
risks a similar outcome, even further compounded by the continued
existence of the cross runway 16/24. Even before a formal investment
appraisal, a runway that will only yield two-thirds of its design
capacity is evidently a bad investment when a fully usable runway
could be built elsewhere.
|
 |
The
EIS high growth forecasts mean that the new runway would only
offer capacity up until 2029, reaching capacity before the useful
life of the pavement and the investment is realised. And that
is before considering the extent to which the expected extra movements
are overstated by the failure to take full account of ground delays.
Full capacity, on EIS figures, may be reached by 2022.
|
 |
The
EIS did not address how long the provision of a new runway would
satisfy future air traffic demand or the 'capacity crunch' that
will affect Dublin Airport if the air traffic forecasts of the
DAA are realised. The second runway investment is unsound because
it allows for no future capacity development that will be required
on present trends as set out in the EIS. When the second runway
reaches capacity, there would be no space left in which to build
further runways. When this capacity crunch becomes obvious, the
government will be faced with the construction of a new international
airport elsewhere, but lands on which to develop an airport capable
of supporting 3 or 4 runways, will have risen hugely in cost and
may even be unavailable. It makes far more economic and commercial
sense to consider the alternative site now when such land is available.
|
 |
Construction
of the second runway, once built, will force future airport development
policy in one specific direction and commit some very long-term
infrastructure investment, for which the new runway may not even
offer sufficient capacity.
|
 |
The
EIS passenger projections ignored the subsidised nature of the
passenger charges at Dublin Airport. The subsidy arises because
passengers do not have to pay market value for the use of the
public land at Dublin Airport. If this subsidy were removed, charges
would rise significantly, with huge impacts on the demand for
the services of that airport and consequently on future capacity
needs at that site. Much of future growth would have to be met
by alternative facilities developed where land is not as expensive
as at Dublin Airport. Such alternatives should be considered now.
They were not adequately considered in this EIS, which ignored
the implications of land values.
|
 |
Additional
Information proposals for "Portmarnock-friendly" use
of the new runway, and set as Condition 5 by FCC in granting approval,
are not workable.
 |
In
the case of the Convention Centre proposed for the Citywest
Hotel near Dublin, the Board decided that it would be inappropriate
and impractical to seek to control the scale of the development
by a condition limiting its use. We believe similarly that
conditions limiting the proposed runway's use are impractical,
unworkable and implausible.
|
 |
The
assignment of aircraft to runways is entirely at the discretion
of ATC and the pilots. Pilots' requests will usually be
granted by ATC.
|
 |
Apart
from weather and safety exceptions, the proposal also allows
air traffic demand to determine operations. As new runway
10L/28R will be the longest runway at the airport, aircraft
requiring a longer runway will always be given permission
to use the north runway. This pressure will inevitably grow.
|
 |
Heavy,
non-stop long-haul departures will be assigned to the new
runway and the DAA will not forego marketing its new capability
to attract cargo operators and long haul air services.
|
 |
Given
the existing arrival and departure tracks over the Irish
Sea and the unbalanced nature of arrivals and departures,
UK traffic (the heaviest route) will dictate departures
on the new runway over Portmarnock, when the winds are easterly.
The air traffic demand caveat was designed for this common
situation. ATC would use 10L for departures for traffic
reasons, regardless of any preferential commitments.
|
|
|

|
No
consideration was given to the place of terminals in the capacity
expansion plans underlying the proposed runway. Because of the capacity
limitation of the ultimate two-runway system, the investment in
two additional passenger terminals as proposed in the Airport Masterplan
would be under-utilised because neither could support long term
growth in passenger traffic or be used to the end of their useful
economic lives, before a new airport will have to be brought into
service. |
Economics (EIS Chapter 6)
 |
No
assessment was made of effects of the runway proposal on Material
Assets (land and property) as required by EIS Directive 85/337/EEC.
This should include an analysis of economic and social impacts.
But:
 |
No
assessment was made of the impact of 10L/28R on the value
of land and property under the new flightpath.
|
 |
No assessment was made of the cost of the buy-out of homes
in St Margaret's in assessing 10L/28R.
|
 |
No
assessment was made of the loss of value to thousands of
homes under and near the flightpath of 10L/28R.
|
|
 |
No
cost benefit analysis was carried out, as required by Department
of Finance, updated and reissued in early 2005. Since October
2005, such an analysis is required for all capital projects estimated
to cost more than €30 million. Although there was no precise
cost threshold at the time, prior to the application for planning
approval, when the runway proposal should have been assessed,
the scale of the project would have made it eligible for cost
benefit analysis under the earlier 1994 guidelines. The term "cost
benefit" appears only once in the EIS in the context of a
system of internal airport transport.
|
 |
Fingal's
director of planning admitted that no economic case had been made
for the runway.
|
 |
No
proper economic assessment was made of alternatives as required
by Department of Finance Guidelines. Conclusions were based on
false and unquantified assertions. Directive 85/337/EEC, Annex
III-2 also requires alternatives to be studied, and the reasons
for the option chosen to be spelled out. This was not done in
an adequate manner.
|
 |
Standard
analysis procedures were violated when the value of land owned
by Dublin Airport was not considered in assessing alternatives
within and without Dublin Airport:
|
| |
 |
Had
such land, and land devalued under the flightpath, been
costed at opportunity cost, the cost of building 10L/28R
would have risen by at least €2.5 billion.
|
 |
In the case of runway 11/29, the need to purchase land for
its extension was a critical cost factor in the decision
in favour of 10L/28R. However, the 11/29 option would have
released hundreds of DAA-owned acres not then needed for
10L/28R. This point was ignored because it favoured the
option to improve 11/29.
|
 |
Though
an improved 11/29 was rejected on (false) cost grounds in
the EIS, a consultant for the FCC claimed that it had been
rejected on safety grounds.
|
|
 |
The
cost of land at alternative sites was not considered when alternatives
were rejected on "cost grounds":
 |
Thousands
of acres of low value former bogland available for a new runway
adjacent to the Greater Dublin Area were ignored in ruling
out that option. Costs were assumed to be the same, or greater
than 10L/28R, when land costs for 10L/28R are at least €2.5
billion. |
|
 |
While
spin-off or multiplier benefits from the Dublin Airport option
were grossly exaggerated, those same benefits were not even mentioned
in the EIS when a new airport at an alternative site was considered:
 |
A
second airport was rejected by the EIS on assumed and exaggerated
cost grounds (€5.5 billion). But, as no benefits were
measured for it, the rejection was groundless. Costs alone
are not a basis for rejection of a proposal. Benefits must
also be measured and compared with those costs.
|
 |
The
economic return from such an airport, public or private,
would be very substantial given its room to grow in an uncongested
environment. Good design could ensure that new residential
communities would not be adversely affected by noise and
air pollution.
|
 |
UPROAR
estimated that such a new airport would yield a 7.4% return
on investment, operating on a passenger charge similar to
the subsidised charge at Dublin Airport and before considering
realistic spin-off and multiplier benefits.
|
 |
If
a new airport were planned for an extensive area of state-owned
former bogland, land values would increase overnight from
a few thousand euros to €0.5 million to €1 million
an acre. Land, surplus to airport needs, could be sold for
development. This would be largesse for the public purse,
which could part-fund a new state airport.
|
 |
Under
the 1998 Air Navigation Act, Dublin Airport, with ministerial
permission, can establish and operate a new airport |
|
Chapter 6 of the EIS, "Employment and Economics", is seriously
flawed:
 |
Cost
benefit methodology was not used.
|
 |
The
methodology used has been criticised by international experts.
It employs sophistry, i.e. plausible but misleading and fallacious
arguments.
|
 |
Job
creation was used as a measure of economic benefit when it is
not a measure of economic benefit in times of near full employment.
Job creation in such an economy leads to labour market overheating
and is a disbenefit.
|
 |
Jobs,
if the runway were not built, were made to "disappear"
by erroneous use of ESRI labour productivity statistics, including
assuming that jobs created by passenger and freight growth would
be average jobs rather than largely service-type jobs subject
to low productivity growth.
|
 |
Indirect
job creation was assumed to be a benefit without considering constraints
due to congestion and other infrastructural impediments in Fingal.
|
 |
No
assessment was made of indirect and direct jobs and other economic
impacts for alternative uncongested sites.
|
 |
No
corrections to the EIS by way of Additional Information were asked
for by FCC, as requested by UPROAR. The FCC is therefore assumed
to agree with the flawed methodology and to condone its conclusions.
|
 |
FCC
consultants further exaggerated these erroneous conclusions. The
same FCC consultant made dubious assumptions about benefits from
tourism, again ignoring the fact that tourism benefits, probably
to a greater extent, would apply to less congested alternative
sites. Research shows that a single dominant gateway (e.g. Heathrow
in the U.K.) is bad for the distribution of tourism benefits to
the regions.
|
 |
DAA
and FCC consultants consistently confused the undoubted value
to the national economy of Dublin Airport with the assumed value
of the proposed runway development, in spite of UPROAR's findings
that the runway was itself a bad investment and an economic loss.
An investment proposal stands or falls on its own merits. It has
to be considered independently of the whole of which it is only
a prospective part.
|
 |
UPROAR's
analysis, using cost benefit analysis methodology, has established
a strong a priori case that this runway will waste at least €3
billion of public and private assets. It also demonstrated that
new airport, built on a well-selected site to serve the Greater
Dublin Area, would be a sound economic and attractive environmental
and social proposition. This work was submitted to the DAA and subsequently
the FCC, but was ignored, despite the onus on these public bodies
to demonstrate the overriding public interest before peoples' rights
are violated. |
National Policy (EIS Chapter 7)
 |
National
aviation policy issues are not addressed at all in the EIS, nor
is any attempt made in the EIS to place this runway proposal in
a national policy context. Policy references are exclusively in
a local context.
|
 |
The
proposal for a second runway is the single largest capital investment
currently planned for any of Ireland's airports. Before any major
and far-reaching decisions are taken to add a new runway at Dublin
Airport, a national plan has to be in place to define how national
air transport should develop in the future, and the roles that
the national and regional airports will play in that development.
High-level endorsement of need and justification is a fundamental
requirement that is plainly lacking.
|
 |
Placing
the decision to implement the second runway at the level of a
local planning authority, without sufficient high-level study
of its context in terms of long-range capacity for the airports
of the Dublin region, and out of context with national civil aviation
development policy, ensures that national interest is not served.
|
 |
However,
there is no adequate national aviation policy in place to guide
proper decision-making. UPROAR was directed to the Statement of
Strategy 2005 - 2007 as the "best steer" on national
aviation policy. A policy document covering a period that runs
out years before the runway is built, is useless.
|
 |
National
Spatial Strategy (NSS) is violated by this runway proposal although
its proponents, in the EIS (7.2.5) and Dublin Airport Masterplan
appeal to selective references in favour of further expansion
of Dublin to make its case. There cannot be any question that
the whole emphasis of the NSS is on rebalancing development away
from Dublin in favour of the regions. If recognition is given
in the NSS to the inevitable role of Dublin and the need for Dublin
to remain competitive, that cannot be taken to permit the central
thrust of NSS to be undermined; i.e. positive discrimination in
favour of the regions. That would lead to a preposterous outcome,
where all proposals to add further to the expansion of Dublin
could be justified by reference to these selectively positive
references in the NSS to the need for, and inevitability, of Dublin's
continued development.
|
 |
Further,
appeals to the NSS references to the importance of Dublin's continued
prosperity, would only have some relevance if the proposal were
positive for Dublin. That is demonstrable not the case in economic,
social and environmental terms.
|
 |
Sustainable
development is development that meets the needs of this generation
without compromising the ability of future generations to meet their
needs. The concept captures the important ideas that development
has economic, social and environmental dimensions which together
can contribute to a better quality of life and will only be sustainable
if a balance is achieved between these three dimensions. If all
three outcomes of a development proposal are negative, no positive
balance can be achieved and the development is categorically unsustainable.
With this runway proposal, there can be no trade-off between economic,
social and environmental positives and negatives, because it economic,
social and environmental effects are all negative. |
Water
(EIS Chapter 11).
 |
The
EIS deals inadequately with potential runoff problems. The runoff
from existing runways and parking flows into the Sluice and Mayne
streams both of which are already "seriously polluted"
according to the EPA. It can be expected that there will be contamination
in the groundwater, especially since infiltration of runoff is
being encouraged.
|
 |
The
Sluice catchment consists mainly of small ditches down the sides
of fields, leading into a lake at Kinsaley, which is already subject
to contamination from discharges from the airport. The outflow
from this lake is the Sluice River, which has already been deepened
to eliminate flooding. It is indicated in the EIS that runoff
from the portion of the runway within the Ward River catchment
area will be directed into the Sluice River Catchment. This will
further exacerbate the problem of the volume of water involved
by effectively increasing the catchment.
|
 |
The
attenuation of runoff to green-field rates, of existing car parks
within the airport complex contributed to flooding in this catchment.
It is likely that the calculated volumes of water involved with
the new runway will entirely overwhelm the Sluice system. Flooding
in the area will be worsened.
|
 |
This
stream flows into Baldoyle estuary, a Nature Reserves and a Special
Areas of Conservation, a Special Protection Area, a National Heritage
Area and a RAMSAR Site and is protected under the Wildlife Act,
1976 and the Habitats Directive (92/43/EEC). The reserve is also
rated as of international importance for Brent Geese.
|
 |
There
will undoubtedly be a significant amount of petroleum oils, hydraulic
fluids and other materials carried by rainwater being discharged
from the facility. This is a recognised problem with motorways,
however the concentration will be higher from a runway due to
the 'point source' of the discharge.
|
 |
There
is no evidence that the foul sewer and the sewage treatment plant
will have the ability to cope with a pulse of contaminated runoff
from de-icing. With the low temperatures involved, it may be expected
to poison the treatment plant leading to major problems for the
treatment plant. |
Road
Traffic (EIS Chapter 13)
 |
The
DAA's consultants used an out-of-date, poorly calibrated model
to assess the runways impacts on traffic in the EIS.
|
 |
The
EIS did not demonstrate that the existing or future proposed road
network and public transport proposals could cater for a much-expanded
service to and from Dublin Airport. The Airport will be difficult
to access by road with lengthy and unpredictable journey times
to and from the airport.
|
 |
No
attempt was made in the EIS to estimate or present the economic
costs of road congestion due to the proposed runway, although
the Dublin Transportation Office's (DTO) traffic model does measure
such costs. UPROAR's estimate of €124 million (NPV) is probably
conservative.
 |
The
Dublin Chamber of Commerce said: "The cost of congestion
to the Greater Dublin Area in 2005 was approximately €2.5bn
and is perhaps the single greatest threat to future investment
in the region and the competitiveness of the capital city.
Congestion affects the quality of life, the cost of doing
business and the quality of the environment." |
|
 |
A
Metro to the Dublin Airport will not resolve the resulting traffic
congestion and the high degree of saturation on the M1 and the
M50. At best, public transport (including the Metro) will only
cater for 40% of airport trips.
|
 |
The
capacity of the M1 motorway, and the road junctions around the
airport will be severely affected regardless of a Metro service
to the Airport.
|
 |
As
found by the Board in the case of the Convention Centre proposed
for the grounds of the Citywest Hotel near Dublin, the proposed
runway development contravenes the policies as set out in the
Regional Planning Guidelines for the Greater Dublin Area 2004-2016
to reduce the overall growth in demand for travel and would, therefore,
be contrary to the proper planning and sustainable development
of the area.
|
 |
In
light of the NRA's objection to the IKEA development at Ballymun
near the M50, on the grounds that it will threaten the benefits
of the M50 upgrade, there is now an overwhelming case for an independent
review of the earlier traffic modelling. This should also include
the impacts from IKEA and the Dublin Port Tunnel, the "Airport
Box" proposed by FCC, as well as the new northern runway.
A DTO 2004 model is now available for this work and the DTO would
be the appropriate Government Agency to undertake the work.
|
 |
The
DAA's Additional Information consultant, RPS MCHugh, agreed that
computer modelling of traffic in the EIS was outdated and should
be repeated with the calibrated DTO 2004 model. This has not been
done.
|
 |
The
same author says that the existing junctions will be over-capacity
in the "opening year of 2010". As the runway could not
open until 2013/14, the road network will be even less able to
cope with the additional load by that time.
|
 |
The
estimated cost of €200 million for the proposed Airport Box
road network was ignored.
|
 |
The
cost of the proposed airport Metro was ignored. |
Air Quality (EIS Chapter 14)
 |
The
EIS assertion that reduced delays for aircraft on the ground "would
contribute to lower emissions from aircraft on the ground, which
would compensate for any slight increase in emissions from the
airport area due to higher aircraft movements" is absurd,
not least because ground delays will increase. (See: "Engineering
and Operations.")
|
 |
It
is likely that the doubling of aircraft movements expected by
2025 will double the volume of pollutants being released. How
can that possibly be eliminated by supposed reduced ground delays?
|
 |
Monitoring
of air quality was performed by the DAA with a resulting lack
of transparency. Projected air quality, if mimicking UK airport
levels, will exceed EU limits.
|
 |
Portmarnock
is downwind of the airport in the path of the prevailing winds.
This fact was presented to the St. Margaret's community by the
DAA as indicating a lesser impact on them, clearly implying a
greater impact on Portmarnock.
|
 |
No
analysis was done in the EIS of the consequences for air quality
of the increase of 35,000 airport-related car movements per day
by 2025. Modern car engine modifications produce higher NOx emissions
per unit of fuel.
|
 |
Heavier
long-haul aircraft which will take off on the longer runway, being
more fuel-efficient, will emit more NOx.
|
 |
The
Dublin City Council Air Quality plan states: "The synergistic
effect of two or more air pollutants on community health is greater
than the sum of the individual effect of each." This effect
was ignored in the EIS. |
Climate Change (EIS Chapter 15).
 |
The
contribution to climate change of the runway development is stated
in the EIS to be "negligible" despite the projected
doubling of aircraft movements, and an increase of 35,000 airport-related
car movements per day by 2025. In addition, modern car engine
modifications produce higher NOx emissions per unit of fuel. No
quantification of the climate affects of these increases was made
in the EIS.
|
 |
The
effects of increased aircraft movements on the emissions of greenhouse
gasses affecting the fulfillment of the Kyoto Protocol commitments
were wrongly analysed.
|
 |
The
EIS assertion that improvements in aircraft engine design and
higher fuel efficiency, "would also contribute to lower greenhouse
gas emissions at the airport over the next 20 years," ignores
the obvious fact that the impact of a doubling of aircraft movements
cannot be offset by increased fuel efficiency, which will not
double. Emissions will certainly increase.
|
 |
Further, NOx, increasingly emitted by more fuel-efficient engines,
has a 310 times higher global warming potential than CO2
|
 |
The
forecasts of increased passenger and freight traffic did not address
the problem of inevitably rising aviation fuel prices due to depleted
resources, nor the recent proposal of the European Parliament Environment
Committee that a revised Emission Trading Scheme (ETS) should cover
all flights through EU airspace. With fuel costs currently 40% of
the cost of an average airline ticket, and rising rapidly, demand
for air travel will become increasingly sensitive to rising fuel
prices. |
Noise (EIS Chapter 16)
 |
In assessing aircraft noise impacts on schools only one study
was referenced, but could not even be identified with confidence
in the literature. All other recent literature was ignored, including
two studies by Haines et al, studies by Franssen et al, Hardoy
et al, and lastly, the "RANCH study by Stansfeld et al, published
in the Lancet in 2005.
|
 |
Many
of the schools in the RANCH study had noise insulation. No analysis
of the ameliorative effect of insulation on aircraft noise damage
was done.
|
 |
Noise
contours based on estimated average noise and UK standards were
presented as definitive.
|
 |
While
previously specifically exempted from noise control, the operation
of the airport will in the future have to comply with EU 2002/49/EC
transmuted into Irish law by S.I. 140 of 2006 (Environmental Noise
Regulations 2006). Although now in effect, that Directive was
ignored.
|
 |
No
assessment was made in the EIS of the impacts on vulnerable communities
such as Prosper Fingal Training Centre Portmarnock, The Arch Club,
and on care homes and nursing homes in the area.
|
 |
No
maximum noise event data was produced in the EIS for the proposed
runway.
|
 |
Although
maximum noise impacts are most relevant at night they are also
very relevant during daytime hours. For example, repeated high
noise events have serious affects on children's development at
school and after school hours. LAmax noise profiles are valid
for the Portmarnock area and laterally related areas, as an indication
of the transitory noise patterns at peak noise level. This option
is recognised in the EU procedures now governing noise measurements
around airports.
|
 |
Daily maximun noise levels exceeding 90 decibels will hit most
of built-up Portmarnock. All Malahide and Swords residents will
suffer at least 70db events, half of them getting hit by 80db
incidents. With over 40 planes an hour using the new runway at
peak hours there will be a horrendous level of noise for many
hours during the day, on top of existing aircraft noise. With
no night curfew in place at Dublin Airport there is nothing to
prevent such abuse continuing throughout the night. A balanced
and objective analysis would have addressed these serious noise
implications. The EIS simply ignored day-time maximum noise impacts.
|
 |
Maximum
noise data for the old main runway, 10R/28L, was used in the EIS
to make night noise appear to decline for "Dublin City"
and in total. That analysis was based on the assumption that 10L/28R
would never be used at night. That curfew condition was not mentioned
elsewhere in the EIS. This argument is another fine example of
EIS sophistry.
|
 |
The
EIS presented average noise data (LAeq) for the new runway. An
I.C.A.O. metric was used to produce these figures, without calibrating
the model against actual observations; no actual noise measurements
were carried out. All results were computer-generated and based
on certification of aircraft. Certified levels may differ from
actual measurements. It was produced without taking stakeholders
views into consideration. This method is not transparent and is
vulnerable to easy manipulation.
|
 |
The
actual operational noise will be different for different weather
conditions and will also depend on ground cover and contours.
Noise mapping needs to be related to actual measurements on the
ground, which take land contours and new housing developments
into consideration. Model data cannot be used for decision-making
because it has not been "ground-truthed" using empirical
data.
|
 |
The
maps produced presuppose that all aircraft will follow the exactly
define path. In practice, many aircraft deviate from this path
by as much as 1 km either side, broadening the noise impact on
either side of the approach path. Average noise levels are therefore
underestimated.
|
 |
The
present and projected population of the airport environs greatly
exceeds the EIS figures. The population adversely affected by noise
in Portmarnock, Malahide, Swords and Kinsaley may be 150,000 by
2025. |
Crash Danger (EIS Chapter 17).
 |
Given
that during the last ten years 82 per cent of the world's jet
aircraft fleet accidents occurred during take off and landing
phases and accounted for 58 per cent of all onboard fatalities
and all third party fatalities, safety is a major issue for local
communities. The EIS treatment of this issue was inadequate.
|
 |
The
EIS applied UK standards to hazard analysis and presumed they
would apply to the Dublin Airport area. It failed to make any
reference to the actual communities in the danger zones or to
attempt to assess the possible consequences for them given their
specific characteristics.
|
 |
No
account was taken of the fact that Portmarnock is a community
of 10,000 people with the highest rate of family occupancy of
any town in the country (nearly 80%).
|
 |
No
account was taken of the fact that two of the country's largest
secondary schools with over 1000 pupils each and only one kilometre
apart, will be under the new flight path. (Portmarnock and Malahide
Community Schools). There are also two primary schools with 700
pupils near the flight-path.
|
 |
No
account was taken of the fact that the centre-line of the new
flightpath will be over a 120-bed hotel with a capacity of 450
guests and staff, just one kilometre from Portmarnock Community
School. There is also a second large hotel 600 metres away.
|
 |
The
ERM Report's Public Safety Zone analysis is accepted without question.
The Outer Safety Zone, which would apply to most of Portmarnock,
would disallow high-density housing development, and the building
of schools, hospitals, hotels and facilities attracting large
numbers of people. In The Netherlands no house building is allowed
within the outer crash zone because of the risk to human life.
|
 |
It
is quite absurd that new flight-paths with the same dangers can
be put over existing ground structures. If new developments under
existing flight-paths are ruled out on safety grounds, why are
new flight-paths over existing communities not ruled out on the
same safety grounds? Why are the former too dangerous and the
latter of no concern? It is wholly unacceptable that the EIS and
Additional Information ignored these concerns. An objective evaluation
would have addressed these unpalatable facts.
|
 |
In
considering options within and without Dublin Airport, the danger
to existing communities under 10L/28R's new flightpath was ignored
when these options were casually ruled out by the EIS. There are
feasible options, which would exclude those dangers, such as a
new airport on a well-chosen site away from established communities.
No account was taken of these dangers, in shadow-cost terms or
otherwise, when opting on false "cost grounds" for the
dangerous 10L/28R option.
|
 |
Aviation
fuel is delivered to the airport by tanker. A doubling in the number
of aircraft movements, with an increase in aircraft size, will require
more than double the fuel, and an increased numbers of tankers to
transport it from Dublin Port. This will add greatly to the danger
to road users of transporting aviation fuel. Such tankers may not
be permitted in the Port Tunnel. No assessment was made of this
increased risk. |
Health (EIS Chapter 18)
 |
The
EIS contains little material on the human health impact of the proposed
development. The EIS conclusion that "The impact upon human
health of the development will be minimal. Climate would not be
affected" are simply unfounded assertions. |
 |
The
methodology used was inadequate. The small-scale desk study done
was not remotely adequate for assessing the health impacts of
a development of the scale proposed.
|
 |
In
its own term the work done was inadequate: the literature referenced
was out of date, and very important recent work was ignored. The
discussion of the possible impacts on the population around Dublin
Airport was cursory.
|
 |
There
were no references to any literature on the human health impacts
of air quality although knowledge of the health effects of air
pollution has increased greatly over the last decade.
|
 |
Large airports have a negative effect on public health. A health
study carried out at the Medical Faculty in Gent University 2002
showed that, over a 10-year period, health costs far exceeded
economic benefits.
|
 |
A
development on the scale of this runway requires a full health impact
assessment (HIA). |
Environment
- General
 |
Directive
85/337/EEC requires that the description of the likely significant
effects of the proposed project on the environment should cover
the direct effects and any indirect, secondary, cumulative, short,
medium and long-term, permanent and temporary, positive and negative
effects of the project. This EIS has failed to meet those stated
requirements. |
|