|
Comments
on RPS Forecast Report - Capacity
The
Forecast Report is focussed on making the case that growth in aircraft
movement demand will reach the point where the existing airside infrastructure
at the airport reaches capacity, and additional airside capacity is
required.
There is little argument in this. At some point in time, regardless
of which air traffic forecast is applied, aircraft movement demand will
reach the practical capacity of the present airside system, despite
any operational improvements that may be made. When this happens, additional
airside capacity in the form of a new runway will inevitably be required.
The Forecast Report suggests that the demand / capacity analysis concludes
that such additional capacity would be required as early as 2008 (high
GDP growth scenario), or as late as 2013 (low GDP growth scenario).
The Centreline forecast (i.e. Medium Growth condition) suggests that
the additional capacity will be required in 2010, when aircraft movements
reach 44 movements per hour.
What the Forecast Report fails to address is the what will be the ultimate
capacity of the 2-parallel runway system, and how much additional time
this will provide for Dublin Airport in terms of airside capacity. Aside
from not dealing with the matter of ultimate 2-runwsy capacity, a critical
failure of the Forecast Report, in discussing the demand/capacity analysis,
is that it does not suggest how even greater capacity would, or could,
be provided at Dublin Airport, when the 2-parallel runways both reach
capacity - at around 80 movements per hour.
A simple review of the extrapolated demand forecast for aircraft movements
shows that the second parallel runway would 'buy' capacity until about
2030 based on the Centreline Forecast. This means, effectively, that
the second runway would add sufficient airside capacity to last only
20 years, but only 15 years if high economic growth is achieved. By
2030, when the airside capacity bought by constructing the second runway
is exhausted, the airport would only be serving just over 44 million
annual passengers.
The Airport Master Plan provides for longer term terminal expansion
but, clearly, any terminal expansion beyond 44 mppa cannot be supported
by the airside system, even if the 2nd parallel runway is built. Expansion
of passenger terminal capacity, and the ability of Dublin Airport to
continue to serve air transport growth beyond 2030, therefore requires
a 3rd, and much later a 4th, runway.
It is very obvious that the Dublin Airport site cannot accept a 3rd
and 4th runway, and further site expansion would not be feasible either.
The clear indication is therefore that the 20-year horizon, beyond implementation
of the 2nd parallel runway, demands that a new airport be developed
- elsewhere - to serve air transport growth in the Dublin region beyond
the capacity limits of the present airport site.
If the utility obtained from constructing a 2nd parallel runway is only
15 to 20 years, and an increase in airside capacity beyond the limits
of the 2nd parallel runway cannot be achieved at the present site, and
development of a new airport would therefore be required, this then
calls into question whether the decision to address the near term capacity
issue by constructing a new runway of limited useful life, is wise in
the first place.
Consultants for UPROAR
|